Additional Utility-Scale Industrial Solar – Proposed in New York State (2022) [Expires Oct 31 2024]

Additional Utility-Scale Industrial Solar
Proposed in New York State (2022)
Plant Name County Nameplate Capacity (MW) Status Planned Operation Date Latitude Longitude
Hecate Energy Albany 2 LLC Albany 20.0 (V) Under construction, more than 50 percent complete 12/2023 42.50791 -73.83651
Hecate Energy Albany County 1 Albany 20.0 (V) Under construction, more than 50 percent complete 12/2023 42.51546 -73.83345
Hecate Energy Gedney Hill Albany 20.0 (P) Planned for installation, but regulatory approvals not initiated 6/2025 42.45173 -73.89284
Alfred Oaks Solar, LLC Allegany 115.2 (P) Planned for installation, but regulatory approvals not initiated 5/2026 42.21000 -77.82000
Cold Creek Solar Allegany 108.0 (P) Planned for installation, but regulatory approvals not initiated 1/2028 42.49500 -78.08200
Kosa Allegany 1.5 (V) Under construction, more than 50 percent complete 11/2023 42.06882 -77.80742
Bakerstand Solar (NY) Cattaraugus 20.0 (P) Planned for installation, but regulatory approvals not initiated 11/2024 42.34421 -78.47842
SunEast Dog Corners Solar Project Cayuga 20.0 (T) Regulatory approvals received. Not under construction 12/2024 42.74430 -76.66531
Empire Solar (NY) Chautauqua 125.0 (P) Planned for installation, but regulatory approvals not initiated 12/2027 42.25960 -79.61420
NY Fredonia 9824 Route 60 Solar Chautauqua 5.0 (V) Under construction, more than 50 percent complete 12/2023 42.43106 -79.30247
South Ripley Solar Chautauqua 270.0 (L) Regulatory approvals pending. Not under construction 12/2024 42.19812 -79.75789
Afton Solar Chenango 5.0 (U) Under construction, less than or equal to 50 percent complete 4/2024 42.24230 -75.53364
Greene Community Solar Chenango 5.0 (T) Regulatory approvals received. Not under construction 4/2024 42.25207 -75.82642
Hecate Energy Columbia County Solar Columbia 60.0 (P) Planned for installation, but regulatory approvals not initiated 11/2025 42.17503 -73.59039
Shepherd’s Run Solar Columbia 60.0 (P) Planned for installation, but regulatory approvals not initiated 12/2025 42.16141 -73.57453
Homer Solar Energy Center Cortland 90.0 (L) Regulatory approvals pending. Not under construction 11/2027 42.65865 -76.09993
Fork in the Road Solar Dutchess 1.4 (L) Regulatory approvals pending. Not under construction 3/2024 41.95000 -73.75000
Elk Street Solar Erie 2.4 (L) Regulatory approvals pending. Not under construction 4/2024 42.85000 -78.85000
NY Grand Island 871 Whitehaven Rd Solar Erie 5.0 (L) Regulatory approvals pending. Not under construction 12/2024 43.02750 -78.92066
NY Lancaster Gunnville Rd Site 1 Solar Erie 5.0 (TS) Construction complete, but not yet in commercial operation 10/2023 42.95263 -78.61796
SunEast Limestone Solar Project Fulton 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 43.01744 -74.25296
Hecate Energy Cider Solar LLC Genesee 500.0 (P) Planned for installation, but regulatory approvals not initiated 12/2025 43.09734 -78.23041
Potic Solar Greene 4.9 (P) Planned for installation, but regulatory approvals not initiated 12/2024 42.29559 -73.90120
SunEast Flat Hill Solar Project Herkimer 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 43.04436 -74.79632
SunEast Grassy Knoll Solar Project Herkimer 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 43.06538 -74.84372
SunEast Hills Solar Project Herkimer 20.0 (T) Regulatory approvals received. Not under construction 12/2024 43.06830 -74.84923
SunEast Watkins Road Solar Project Herkimer 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 43.06127 -75.05584
ASA Clayton NY Solar I LLC Jefferson 1.3 (V) Under construction, more than 50 percent complete 11/2023 44.16176 -76.10899
FFP – NY Game Farm Jefferson 5.0 (U) Under construction, less than or equal to 50 percent complete 4/2024 44.01276 -76.00873
Greens Corners Solar Jefferson 120.0 (P) Planned for installation, but regulatory approvals not initiated 3/2025 43.93590 -75.97268
Sandy Creek Solar Jefferson 20.0 (P) Planned for installation, but regulatory approvals not initiated 6/2025 43.81283 -76.06884
Tracy Solar Energy Center Jefferson 119.0 (L) Regulatory approvals pending. Not under construction 11/2027 44.17594 -75.98513
Copenhagen Solar Lewis 4.3 (V) Under construction, more than 50 percent complete 10/2023 43.86310 -75.71931
Hatchery Solar Livingston 20.0 (P) Planned for installation, but regulatory approvals not initiated 7/2025 42.97658 -77.76974
Highbanks Solar Livingston 20.0 (P) Planned for installation, but regulatory approvals not initiated 10/2025 42.73723 -77.91431
Horseshoe Solar Energy Livingston 180.0 (U) Under construction, less than or equal to 50 percent complete 12/2025 42.57076 -77.45296
NY Geneseo 3240 W Lake Rd Solar Livingston 5.0 (V) Under construction, more than 50 percent complete 12/2023 42.84721 -77.71827
FFP – NY Werner Monroe 5.0 (V) Under construction, more than 50 percent complete 12/2023 42.96606 -77.68387
High River Energy Center, LLC Montgomery 90.0 (L) Regulatory approvals pending. Not under construction 5/2024 42.90186 -74.13273
Mill Point Solar Montgomery 250.0 (P) Planned for installation, but regulatory approvals not initiated 11/2025 42.91910 -74.34116
Mohawk Solar Montgomery 90.5 (L) Regulatory approvals pending. Not under construction 11/2024 42.88713 -74.63781
SunEast Tabletop Solar Project Montgomery 80.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 42.95950 -74.56680
Slayton Settlement Road Solar Niagara 5.0 (V) Under construction, more than 50 percent complete 1/2024 43.20356 -78.64543
Slayton Settlement Road Solar Niagara 2.0 (V) Under construction, more than 50 percent complete 1/2024 43.20356 -78.64543
Eureka North Solar Oneida 3.5 (V) Under construction, more than 50 percent complete 12/2024 43.12887 -75.41637
Eureka South Solar Oneida 5.0 (V) Under construction, more than 50 percent complete 12/2024 43.13071 -75.41617
SunEast Skyline Solar Project Oneida 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 43.06307 -75.45195
NY Sorrell Hill II CSG Onondaga 5.0 (TS) Construction complete, but not yet in commercial operation 11/2023 43.14672 -76.35467
Source Power II – Taft Onondaga 3.7 (V) Under construction, more than 50 percent complete 10/2023 43.12198 -76.04235
Summit – Cicero Onondaga 5.0 (V) Under construction, more than 50 percent complete 11/2023 43.20000 -76.12000
SunEast Clay Solar Project Onondaga 50.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 43.19255 -76.17360
Route 5 & 20 Community Solar Farm Ontario 2.3 (L) Regulatory approvals pending. Not under construction 6/2024 42.89900 -77.46100
State Route 64N Community Solar Farm Ontario 1.2 (T) Regulatory approvals received. Not under construction 5/2024 42.91500 -77.45400
SunEast Manchester Solar Project Ontario 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 42.95832 -77.19503
Mannys Corners Solar 1 LLC Orange 4.9 (TS) Construction complete, but not yet in commercial operation 12/2023 42.96400 -74.14440
Northline Solar Rensselaer 4.0 (V) Under construction, more than 50 percent complete 11/2023 42.86910 -73.61530
SunEast Hilltop Solar Project Rensselaer 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 42.80861 -73.64046
NY8 – ELP Stillwater Solar Saratoga 20.0 (V) Under construction, more than 50 percent complete 10/2023 42.92623 -73.71147
Glenville Solar Schenectady 4.3 (V) Under construction, more than 50 percent complete 11/2023 42.83949 -73.93256
NY8 – Teichos Pattersonville Schenectady 20.0 (U) Under construction, less than or equal to 50 percent complete 11/2023 42.88080 -74.09510
East Point Energy Center, LLC Schoharie 50.0 (T) Regulatory approvals received. Not under construction 3/2024 42.46137 -74.33509
NY Beaver Dams Dix 1239 Duvall Rd Solar Schuyler 5.0 (L) Regulatory approvals pending. Not under construction 11/2024 42.29465 -76.94717
Halsey Lane Solar Seneca 5.0 (T) Regulatory approvals received. Not under construction 12/2023 42.60397 -76.83834
ASA DeKalb NY Solar I LLC St Lawrence 5.0 (V) Under construction, more than 50 percent complete 10/2023 44.49209 -75.24480
ASA DeKalb NY Solar II LLC St Lawrence 3.0 (V) Under construction, more than 50 percent complete 10/2023 44.48816 -75.24438
ASA DeKalb NY Solar III LLC St Lawrence 3.3 (V) Under construction, more than 50 percent complete 10/2023 44.42411 -75.37919
ASA Gouverneur NY Solar I LLC St Lawrence 1.5 (V) Under construction, more than 50 percent complete 10/2023 44.39085 -75.44324
ASA Gouverneur NY Solar II LLC St Lawrence 4.0 (V) Under construction, more than 50 percent complete 10/2023 44.36009 -75.42747
NY Lancaster Shisler Rd Site 2 Solar St Lawrence 5.2 (TS) Construction complete, but not yet in commercial operation 10/2023 44.67888 -74.96407
NY Potsdam 28 Hamilton St. Solar St Lawrence 4.4 (TS) Construction complete, but not yet in commercial operation 11/2023 44.67888 -74.96407
SunEast Fariway Solar Project St Lawrence 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 44.63516 -75.44118
Chidsey Hill Road Solar Steuben 3.0 (T) Regulatory approvals received. Not under construction 12/2023 42.57306 -77.16598
Clear View Solar Steuben 20.0 (P) Planned for installation, but regulatory approvals not initiated 9/2025 42.57062 -77.46378
Mahany Steuben 3.0 (V) Under construction, more than 50 percent complete 11/2023 42.46994 -77.69541
Wheaton-STEU Steuben 5.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 42.55582 -77.41701
Manorville II Suffolk 0.6 (L) Regulatory approvals pending. Not under construction 10/2024 40.83400 -72.78190
Day Hollow Road Solar Tioga 5.0 (T) Regulatory approvals received. Not under construction 12/2023 42.11305 -76.17806
SunEast Valley Solar Project Tioga 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 42.08380 -76.24770
Magruder Solar Ulster 5.0 (U) Under construction, less than or equal to 50 percent complete 10/2023 41.60294 -74.13770
West Shore Solar LLC Ulster 2.4 (L) Regulatory approvals pending. Not under construction 3/2024 41.80327 -73.96494
Bald Mountain Solar Washington 20.0 (P) Planned for installation, but regulatory approvals not initiated 6/2025 43.13520 -73.56470
FFP – NY Burch Washington 2.5 (V) Under construction, more than 50 percent complete 11/2023 43.32265 -73.46798
SunEast Highview Solar Project Wyoming 20.0 (P) Planned for installation, but regulatory approvals not initiated 12/2024 42.70035 -77.99672
Andy Arthur, 11/8/23 Source: EIA 860 Data (2022)

Data Source: Energy Information Agency, Preliminary Monthly Electricity Generator Facilities EIA-860M, Released Septmber 2023. Get the data: eia.gov/electricity/data/eia860m