Here is a listing of the industrial solar facilities currently operating in Albany County.

Plant Name Entity Name Nameplate Capacity (MW) Operating Month Operating Year Latitude Longitude Google Map Bing Map
Owens Corning at Bethlehem Constellation Solar Holding, LLC 2.0 10 2013 42.586944 -73.865000 Map Map
Bethlehem – East DG Bethlehem Solar, LLC 1.7 3 2016 42.539006 -73.824300 Map Map
Bethlehem – West DG Bethlehem Solar, LLC 1.0 3 2016 42.539006 -73.824300 Map Map
Guildlerland CSG Forefront Power, LLC 2.0 12 2018 42.727288 -74.000810 Map Map
Knaggs Brothers Farm Dynamic Energy Solutions, LLC 3.9 12 2018 42.730350 -73.969100 Map Map
Bethlehem Solar Forefront Power, LLC 1.7 6 2019 42.601145 -73.887420 Map Map
Westerlo NY 1 Westerlo NY 1, LLC 2.0 1 2020 42.438220 -74.015890 Map Map
Medusa NY 1 Medusa NY 1, LLC 2.0 6 2020 42.466286 -74.099530 Map Map

Below is the listing of two additional proposed industrial solar facilities for Albany County.

Plant Name Entity Name Nameplate Capacity (MW) Planned Operation Month Planned Operation Year Status County Latitude Longitude Google Map Bing Map
Hecate Energy Gedney Hill Hecate Energy Gedney Hill LLC 20.0 6 2022 (P) Planned for installation, but regulatory approvals not initiated Albany 42.451733 -73.892840 Map Map
Hecate Energy Albany County 1 Hecate Energy Albany 1 LLC 20.0 6 2022 (P) Planned for installation, but regulatory approvals not initiated Albany 42.515459 -73.833450 Map Map

Data Source: Preliminary Monthly Electric Generator Inventory, April 2021. https://www.eia.gov/electricity/data/eia860m/

Map: Dobbins Memorial State Forest
Map: Cattaraugus State Forest

Operating and Under Construction Industrial Solar Facilties in New York State – April 2021

This interactive map shows currently operating (green), under construction more then 50% complete (yellow), under construction less then 50% complete (red) industrial solar facilities (multi-acre, 1+ MW nameplate) in New York State as of April 2021, as reported by the Energy Information Agency as of June 24, 2021 -- there is a two month lag in the data for compilation and error checking.

Data Source: Energy Information Agency, Preliminary Monthly Electricity Generator Facilities EIA-860M, Released June 24, 2021. Get the data: eia.gov/electricity/data/eia860m

Map: Black Pond Wildlife Management Area
Terrain Map: Proposed Exit 25 Interchange with Interstate 88
Map: South Mountain State Forest